Final B112 Transformer Area PCB Cleanup and Removal Action Implementation Summary Report is now available

February 24, 2023

The Final B112 Transformer Area PCB Cleanup and Removal Action Implementation Summary Report is now available on the Publications Page.

This report presents a summary of the soil removal action completed at the B112 transformer site located west of building 112 at the Richmond Field Station in December 2021, and February and March 2022.

Resources

Final Implementation Report
DTSC Approval Letter