Final Removal Action Workplan Available

July 21, 2014

The DTSC approved July 18, 2014 Final Removal Action Workplan, University of California Berkeley, Richmond Bay Campus, Research, Education, and Support Area (RES) and Groundwater within the Former Richmond Field Station Site (RAW) is now available for download from the Publications page of this website. The RAW establishes the remedial goals and final remedy including prescriptive requirements and land use controls (LUCs) for all RES soils and groundwater at the portions of the Richmond Bay Campus that were determined to require additional removal actions based on site characterization activities. The RAW also includes a Soils Management Plan to be used for future construction and other soil disturbance which supports the implementation of LUCs by providing a framework to prohibit uncontrolled soil excavation or disturbance activities.