2009.06.01 DTSC Risk Assesssment for Coastal Cleanup Volunteer in the Meeker Slough Area |
DTSC |
2009 |
Agency Letter |
2009.06.04 RFS Weeds Worker Training Manual |
UC Berkeley |
2009 |
Report |
2009.06.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2009 |
Report |
2009.06.22 Workplan for Evaluation of Pre-Construction Conditions in Soil, Meade By-pass Roadway |
PES Environmental, Inc |
2009 |
Report |
2009.07.10 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2009 |
Report |
2009.07.31 Tsunami Inundation Map for Emergency Planning with Berkeley Global Campus |
Contra Costa County |
2009 |
Figure |
2009.08.12 Year 4 Monitoring Report for the Western Stege Marsh Restoration Project |
Tetra Tech |
2009 |
Report |
2009.08.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2009 |
Report |
2009.09.14 Response to Comments from DTSC for the Second Addendum to the Treatability and Pilot Study Work Plan for Localized Occurrences of Volatile Organic Compounds in Groundwater, Lots 1 and 2 |
LFR |
2009 |
Report |
2009.09.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2009 |
Report |
2009.10.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2009 |
Report |
2009.11.02 Results of Evaluation of Pre-Construction Conditions in Soil, Meade By-pass Roadway |
PES Environmental, Inc |
2009 |
Report |
2009.11.16 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2009 |
Report |
2009.12.07 Results of Evaluation of Pre-Construction Conditions in Soil Meade By-Pass Roadway, Richmond, California, Approval Letter |
DTSC |
2009 |
Agency Letter |
2009.12.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2009 |
Report |
2010.01.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.02.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.02.26 Letter Work Plan for Step-Out Sampling Locations on the University Of California Richmond Field Station, MW-25 Pilot Test Area, Lots 1 and 2, Former Zeneca Facility |
LFR |
2010 |
Report |
2010.03.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.03.17 Final Release: Public Health Assessment Evaluation of Exposure to Contaminants at the University of California, Berkeley, Richmond Field Station (PHA) |
Department of Public Health |
2010 |
Report |
2010.04.15 Final Field Sampling Workplan Appendix B, Health and Safety Plan |
Tetra Tech |
2010 |
Report |
2010.04.15 Final Field Sampling Workplan: Appendix A, Quality Assurance Project Plan |
Tetra Tech |
2010 |
Report |
2010.04.15 Final Phase I Groundwater Sampling Field Sampling Workplan |
Tetra Tech |
2010 |
Report |
2010.04.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.05.17 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.05.26 Final Phase I Groundwater Sampling Field Sampling Workplan; Appendix A, Quality Assurance Project Plan, and Appendix B, Health and Safety Plan, Approval Letter |
DTSC |
2010 |
Agency Letter |
2010.06 Appendix A: Historical Maps and Imagery Western Stege Marsh Restoration Project Site |
Kamman Hydrology & Engineering, Inc |
2010 |
Figure |
2010.06.02 Final Phase I Groundwater Sampling Field Sampling Workplan |
Tetra Tech |
2010 |
Report |
2010.06.02 Final Phase I Groundwater Sampling Field Sampling Workplan, Appendix A, Quality Assurance Project Plan |
Tetra Tech |
2010 |
Report |
2010.06.02 Final Phase I Groundwater Sampling Field Sampling Workplan, Appendix B, Health and Safety Plan |
Tetra Tech |
2010 |
Report |
2010.06.02 Final Phase I Groundwater Sampling Field Sampling Workplan, Figure 7 Groundwater Sampling Locations |
Tetra Tech |
2010 |
Figure |
2010.06.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.07.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.08.16 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.09.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.09.30 Fifth Annual Monitoring Report East Stege Marsh |
Arcadis |
2010 |
Report |
2010.09.30 Year 5 Monitoring Report for the Western Stege Marsh Restoration Project |
Tetra Tech |
2010 |
Report |
2010.09.30 Year 5 Monitoring Report for the Western Stege Marsh Restoration Project, Attachment 1: Year 5 Hydrologic Monitoring Report |
Kamman Hydrology & Engineering, Inc |
2010 |
Report |
2010.09.30 Year 5 Monitoring Report for the Western Stege Marsh Restoration Project, Attachment 2: Vegetation Monitoring Report |
May & Associates, Inc |
2010 |
Report |
2010.10 RFS Invasive Weeds Annual Calendar |
UC Berkeley |
2010 |
Report |
2010.10.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.11.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2010.11.19 Year 5 Monitoring Report, DTSC Comments |
DTSC |
2010 |
Agency Letter |
2010.11.24 Letter Work Plan to Evaluate Groundwater in Select Areas at the University of California Richmond Field Station, Response to Comments |
Arcadis |
2010 |
Report |
2010.12.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2010 |
Report |
2011.01.12 Draft Phase I Groundwater Sampling Results Technical Memorandum |
Tetra Tech |
2011 |
Report |
2011.01.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2011 |
Report |
2011.02.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2011 |
Report |
2011.02.25 Response to Department of Toxic Substances Control’s Comments on the “Third Addendum to the Treatability and Pilot Study Work Plan for Localized Occurrences of Volatile Organic Compounds in Groundwater, Lots 1 and 2, Former Zeneca Facility |
Arcadis |
2011 |
Report |
2011.03.08 Third Addendum to the Treatability and Pilot Study Work Plan for Localized Occurrences of Volatile Organic Compounds in Groundwater, Lots 1 and 2, Former Zeneca Facility Approval Letter |
DTSC |
2011 |
Agency Letter |