2012.08.10 Final Phase III Field Sampling Plan |
Tetra Tech |
2012 |
Report |
2018.07.31 Semi-Annual Groundwater and Surface Water Monitoring Report, January 1 through June 30, 2018 |
Terraphase |
2018 |
Report |
2021.08.19.RFS B277 Soil Sampling Summary Letter |
Tetra Tech |
2021 |
Report |
2005.07.08 Summary of PCB Results Richmond Field Station |
BBL |
2005 |
Report |
2008.07.11 Memorandum for a Time-Critical Removal Action at Two Campfire Locations in the Western Transition Area |
Tetra Tech |
2008 |
Report |
2012.02.01 Final, Revision 1 Phase I April 2011 Groundwater Sampling Results Technical Memorandum |
Tetra Tech |
2012 |
Report |
2009.01.26 Western Stege Marsh Restoration Project: Vegetation Monitoring Report - 2008 |
May & Associates, Inc |
2009 |
Report |
2012.09.17 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2012 |
Report |
2009.07.10 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2009 |
Report |
2015.12.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2015 |
Report |
2012.01.20 Technical Memorandum for Well Closures |
Tetra Tech |
2012 |
Report |
2010.03.17 Final Release: Public Health Assessment Evaluation of Exposure to Contaminants at the University of California, Berkeley, Richmond Field Station (PHA) |
Department of Public Health |
2010 |
Report |
2012.09.10 Pilot Study Summary Report for the In Situ Treatment of Volatile Organic Compounds in Groundwater, 2011 Injections |
Arcadis |
2012 |
Report |
2022.03.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2022 |
Report |
2018.11.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2018 |
Report |
2018.06.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2018 |
Report |
2019.06.10 NRLF Phase 4 Updated Sampling Report |
Tetra Tech |
2019 |
Report |
2012.12.11 Final Ambient Metals Evaluation Aluminum, Cobalt, Manganese, and Nickel Technical Memorandum |
Tetra Tech |
2015 |
Report |
2009.05.26 Implementation Summary Report for a Time-Critical Removal Action at Two Subareas in the Western Transition Area |
Tetra Tech |
2009 |
Report |
2015.07.10 RFS Corporation Yard Removal Action Plans |
Tetra Tech |
2015 |
Report |
2011.12.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2011 |
Report |
2013.03.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2013 |
Report |
2009.12.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2009 |
Report |
2016.11.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2016 |
Report |
1990.05.21 Removal Site Evaluation of Mercury in Soil and Groundwater at Former Mercury Fulminate Area |
Jonas & Associates Inc |
1990 |
Report |
2006.11.02 Field Implementation Plan for Surface Water, Stormwater and Sediment Monitoring |
Tetra Tech |
2006 |
Report |
2016.01.14 DTSC Update Richmond Southeast Shoreline Sites |
DTSC |
2016 |
Report |
2012.09.05 Draft Phase I November 2010 through April 2012 Groundwater Sampling Results Technical Memorandum |
Tetra Tech |
2012 |
Report |
2017.03.24 Proposed Continued Groundwater Monitoring Locations for 2017 |
Tetra Tech |
2017 |
Report |
2007.03.30 Work Plan for Additional Groundwater Investigation and Piezometer Installation, Updated Table 1 |
LFR |
2007 |
Report |
2020.07.14 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2020 |
Report |
2022.07.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2022 |
Report |
2008.11.21 (3) Final Current Conditions Report Appendices A, B, D, E, F, G, H, I, K & L |
Tetra Tech |
2008 |
Report |
2017.07.17 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2017 |
Report |
2006.02.07 Background Air Monitoring at Building 478 Attachments A-C |
UC Berkeley |
2006 |
Report |
2009.03.19 Year 3 Monitoring Report for the Western Stege Marsh Restoration Project |
Tetra Tech |
2009 |
Report |
2018.10.15 Final Phase V Sampling Results Technical Memorandum Western Stege Marsh |
Tetra Tech |
2018 |
Report |
2005.11.30 Soil Vapor Study Results for Building 240 at the Zeneca/former Stauffer Chemical Site |
DTSC |
2005 |
Report |
2012.04.16 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2012 |
Report |
2013.08.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2013 |
Report |
2015.02.17 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2015 |
Report |
2011.01.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2011 |
Report |
2015.10.06 Phase IV, EPA Meadow North, Supplementary PCB Sampling Results |
Tetra Tech |
2015 |
Report |
2018.05.21 Annual Groundwater and Surface Water Monitoring Report, January 1 Through December 31, 2017, Campus Bay, Response to Comments |
Terraphase |
2018 |
Report |
2020.09.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2020 |
Report |
2021.10.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2021 |
Report |
2023.03.15 Richmond Field Station Monthly Summary Report |
UC Berkeley |
2023 |
Report |
Coastal Prairie mow guidelines and maps |
UC Berkeley |
2008 |
Report |
2004.11.22 Status Report on Polychlorinated Biphenyls in the Western Storm Drain |
UC Berkeley |
2004 |
Report |
2001.11.13 Evaluation of the Zeneca Richmond Facility as Salt Marsh Harvest Mouse Habitat |
H.T. Harvey & Associates |
2001 |
Report |